On a firm-fixed-price prime contract, the government usually isn’t asking for earned value. That doesn’t mean the prime can stop paying attention, especially when a large share of the work is subcontracted.
Take a program where one subcontractor holds close to half the scope. If that sub is fixed-price to the prime too, an overrun is the sub’s problem on paper. A slip isn’t. When a sub that size falls behind, the prime’s schedule moves with it, and the prime’s own costs keep running while it waits. And if the overrun gets big enough, it doesn’t stay the sub’s problem for long.
No requirement, same problem
On a cost-type contract, the EVM clause forces some discipline whether anyone likes it or not. There’s a baseline, a monthly cycle, and somebody outside the company looking at the numbers. On a fixed-price prime most of that goes away. The customer may still ask for a schedule and some periodic reporting, but nobody is checking whether the prime can see inside its own subcontract.
So the prime is the only one who needs that visibility. When a big part of the program is in someone else’s hands, the prime’s margin depends on it.
What tends to happen
The prime manages its own work closely and treats the sub more like a vendor. Monthly calls, a status slide, invoices against milestones.
Milestone payments tell you what the sub has billed. They don’t tell you how much work is left or whether the next milestone is realistic. When a big piece of the program is in that subcontract, finding out late is expensive, and on a fixed-price prime contract there’s nobody to pass the prime’s added cost to.
The sub is usually fixed-price to the prime, too, so they have their own reasons to keep a problem quiet until they can’t.
What it takes
The prime needs a way to see real progress inside the subcontract, and that has to be written into the subcontract terms, not left as a favor the sub can stop doing. It doesn’t have to be a full EVMS. It does have to be tied to actual work, and it has to roll up into the prime’s own schedule and estimate at completion so there’s one honest number for the whole program.
How much to ask for, and how to set it up so the sub can live with it, is different on every program.
If you’re working through this now, I’m glad to talk it through.