The September 14 memo is a Department of War memo. If your contracts are with NASA or DOE, your EVM requirements didn’t change.

I wrote last month about what the memo does to system validation on DoW contracts. This one is about NASA and DOE work.

What the memo covers

The memo directs DoW components. It doesn’t change the FAR, the NASA FAR Supplement, or DOE Order 413.3B.

NASA’s EVMS clause, 1852.234-2, reads the same as it did before the memo. Under NASA’s June 2025 class deviation, EVM applies at $50 million and a compliance determination is required at $100 million. DOE still requires contractor certification under 413.3B, and DOE’s Office of Project Management still does those reviews itself for projects at $100 million and above.

Where NASA is different

DOE has its own certification process and its own people to run it.

NASA does some reviews itself, mostly for universities and labs where DCMA isn’t on site. For the large contractors, NASA uses DCMA. An MOU between the two agencies lets NASA request DCMA for compliance reviews and surveillance, and the NASA FAR Supplement tells contracting officers to bring in the cognizant DCMA office when determining system compliance.

DCMA is part of the Department of War. The memo tells the Department to “retire the separate government system validation regime.” It doesn’t mention NASA or the MOU, and I doubt NASA was on anyone’s mind when it was written.

Right now DCMA is still reaching out to schedule NASA surveillance, so nothing has changed yet. But the memo also tells the Department to realign contract oversight and deal with the workforce effects, and those actions are due December 13. If DCMA’s EVMS group gets smaller, NASA will have to decide who does its reviews. I’d keep an eye on that.

I could be wrong about how much this matters. I’d still rather know early.

Contractors with both

A lot of companies run one EVMS for both DoW and NASA contracts. If DoW stops validating that system, the NASA requirement doesn’t go away. The system still has to be compliant, and problems that build up on the DoW side will show up on the NASA side eventually, usually at an IBR or a surveillance review.

What to do now

Keep your system description up to date and keep doing your own internal surveillance.

Go by your contract clauses. The memo doesn’t change them, and a no-cost modification on a DoW contract doesn’t change your NASA contract either.

If DCMA did your last NASA compliance review, ask your NASA EVM point of contact who’s expected to do the next one.