DoD policy discourages the government from requiring earned value on firm-fixed-price contracts, and a program office needs a waiver to put it on contract. That’s a limit on what the government can ask for. Nothing in it stops a contractor from using earned value on its own. The policy made sense when fixed-price was saved for work everybody understood. It’s a different picture now. The government wants fixed-price to be the default, so more complicated work is going out with no EV requirement and all the cost risk sitting with the contractor.
That said, EVMS was never about checking a requirement box. It’s good project management. If you have a good system and solid procedures, it isn’t hard to run. A DCMA requirement just makes sure you’re using your system the way you say you are.
So nobody’s going to make you use earned value on fixed-price work. There are still three good reasons to do it.
1. Your system has to be how you do business
If your site has cost-type programs with an EVMS requirement, the system has to be how your site actually manages work, not just a monthly report on the programs that require it. On NASA and DOE work, the system still gets reviewed, and reviewers can tell the difference fast. It doesn’t take long to see whether your executives use the earned value data to manage, or whether the program office puts it together because the customer asked. On DoD work, the separate system validation is going away, so nobody may be checking that for you anymore. That’s on you now.
Now picture a site where the cost-plus programs run on control accounts, work authorizations and monthly variance analysis, and the fixed-price programs run on a spreadsheet and somebody’s gut. That’s two ways of doing business. It tells a reviewer the EVMS is something you do because the contract says so.
DoD’s own interpretation guide expects contractors to build their EVMS on the management processes and tools they already use. If the system really is your process, it should show up on all your work, not just the contracts that require it.
It’s also easier. You keep one set of procedures and tools, and CAMs who move from a cost-plus program to a fixed-price one don’t have to learn a second way of working.
2. You’re the one carrying the risk
On a cost-plus job, an overrun is a problem. On a fixed-price job, it’s your money. Every dollar over the price comes straight out of your margin.
That’s why the early indicator matters more here. By the time the actual costs look bad, you’ve usually been losing money for a while. Earned value shows you the gap between what you’ve spent and what you’ve actually accomplished, while there’s still time to fix it.
A well-defined baseline also helps keep scope creep in check. When everybody knows what’s in the plan and what it’s budgeted for, extra work gets noticed before you’ve already absorbed the cost.
3. Any project that runs longer than a year
Forget the government for a minute. If a project runs longer than a year, it’s worth managing with earned value, whether it’s a government contract, a construction job or commercial work.
On a short job, you’ll know how it went soon enough. On a long one, a problem has plenty of time to grow before anybody notices. Spending looks fine. Percent complete looks fine. Then somebody finally does the math, and the estimate at complete jumps.
Earned value catches that earlier. It compares what you planned to do, what you actually got done and what it cost to get there. Once you have a few months of performance behind you, the trend is hard to argue with, and there’s still time to do something about it.
What it looks like on fixed-price work
You don’t need the full compliance package to get the value. You need the basics, done honestly:
- A work breakdown structure that covers all the work, broken down far enough that somebody owns each piece.
- A schedule and a time-phased budget, so you know what was supposed to be done and when.
- An objective way to claim progress, with quantifiable backup data to support it. Not somebody’s opinion of percent complete.
- A monthly look at cost and schedule variances, with root cause analysis and corrective actions for the ones that matter, plus an updated estimate at complete.
- Change control, so the baseline still means something six months in.
If you already run an approved system on your cost-type work, you have everything you need. Use the same procedures and tools, and scale the reporting to what the program actually needs.
If your fixed-price work is running outside your system, or you don’t have a system at all, getting started doesn’t take much. SMJ Consulting helps contractors set up earned value that fits how you do business. That can mean a scaled-down approach on one fixed-price job, or bringing all your programs under the same system. If your team is new to earned value, our EVMS Fundamentals course covers the basics. Get in touch if you want to talk it through.